Hi
We are planning to do a migration for our biggest vm (1 os, 4 additional drives totaling 6 TB) using live migration. Other migration for small vm (less than 100GB went smooth,single drive).
Since v2v is single threaded this will likely take significant time. I also understand the cutover needs to happen manually if its live migration.
What I am trying to understand when is the exact time i should do the cutover to minimize the downtime. We are OK for couple of hours of downtime, say shutdown old VM at 95% progress of conversion? But a guidance on this is appreciated.